My father-in-law signed a home repair contract with a contractor on 11/15 and paid a $500 deposit. The contract states the start date as 11/20 and completion date as 11/21. The contractor has not started the work, nor contacted my father-in-law to provide a revised schedule, despite repeated promises to do so. The contractor claims they cannot start due to a family emergency. My father-in-law wants to cancel the contract and is willing to pay the 21% 'Breach' fee indicated in the agreement, but wants to ensure they cannot force him to pay the entire contract amount. What are his rights and options?

December 28th, 2024

Renee R. answered

The contractor has already breached the contract by failing to perform under the agreed timeline, so...